Explain in detail the whole process of space frame aerial closing

 


1. After the grid structure is installed at high altitude, the distance between the grid and the support should be adjusted. For this reason, several groups of chain jacks should be installed above the grid for horizontal adjustment.

2. Check the overall elevation of the grid to prevent uneven height. The elevation and horizontal distance should become one end firstly, and the steel tube should be inserted for connection. Tighten the inverted chain on one side and loosen the inverted chain on the other side so that the distance gradually becomes appropriate.

3. After the adjusted bar on one side is fixed gradually, relax the inverted chain on the other side and continue to fine-tune the elevation of the grid on the other side. The fixed side of the grid should also be observed while adjusting to prevent open welding

4. After adjusting the elevation of the grid frame in the other side , tighten the distance with inverted chain, check the positioning condition preliminarily, insert the plug rod and fix it with spot welding after it is basically correct. Note that the spot welding plug rod should have a certain slope to ensure the center of the space frame is slightly higher than the support.

5. Check all dimensions of the space frame after the closing points of the bars around the space frame are fixed, and weld them in accordance with the welding procedure.

LF is a professional manufacturer and engineering company for space frame and steel structure projects.Do you have a construction project we can help with? We are always ready to help you!Website:www.cnxzlf.com

评论

此博客中的热门博文

Shape of steel space frame structure

Types of steel space frame structure roof

Space frame dome structure